
FFT provided independent quality inspections and Clerk of Works support for a programme including roof covering renewals, replacement windows and doors, loft and cavity wall insulation, electrical upgrades, boiler replacements, ventilation improvements and associated repairs across properties throughout the estate.
The client
The Royal Borough of Greenwich (RBG) is a London borough in Southeast London. The council provides vital services including housing, education, social care and community support to their 25,000 leaseholders and tenants. RBG’s focus is on improving the quality of life and opportunities for all residents.
The project
The programme included roof covering renewals, replacement windows and doors, loft and cavity wall insulation, electrical upgrades, boiler replacements, ventilation improvements and associated repairs across properties throughout the estate.
Given the scale of the programme and the range of work streams involved, the client required independent quality assurance to provide confidence that works were being delivered to the required standards before handover.
Our role
FFT provided independent quality inspections and Clerk of Works support throughout delivery.
Our team undertook regular site inspections, monitored workmanship, reviewed completed installations, identified defects and snagging items, and verified that works were completed in accordance with project requirements. We worked closely with both the client and contractor to ensure quality remained a priority throughout the programme.
Services provided
The challenges
Maintaining consistent quality across a large programme of occupied homes required careful monitoring and regular site presence.
The project involved multiple work streams, changing site conditions and property-specific challenges, all of which needed to be managed while keeping work progressing and minimising disruption to residents.
Added value
FFT’s inspections provided an independent assessment of quality at every stage of delivery. By identifying issues early, monitoring corrective actions and reviewing completed works before handover, we helped reduce defects, improve consistency and provide the client with confidence that the required quality standards were being achieved.
The project also delivered wider community benefits through the involvement of Charlton Athletic Community Trust (CACT), including the refurbishment of a local junior football club clubhouse. This helped enhance facilities for local young people and supported the long-term sustainability of grassroots sport within the community.
The outcome
FFT supported the successful delivery of the planned works programme through a structured quality assurance approach.
Our inspection regime helped maintain standards across multiple work streams, supported effective defect management and provided independent verification of completed works, contributing to improved outcomes for both the client and residents.